Tarbela Ghazi: The Tarbela Dam’s fourth expansion plan’s 17th unit has been completed, according to a news source. The unit’s test run has been initiated and the proper launch will be held on 25th February, 2018 by Prime Minister Shahid Khaqan Abbasi.
The mentioned units will be able to produce 470 Mega Watts of electricity. According to the consignment’s schedule issued under this plan, Tarbela Dam’s fourth expansion plan’s Unit 16 will be completed on 25th April this year, and Unit 15 will be completed on 30th June. As soon as they are operational, there will be an increase of 1,410 Mega Watts of electricity. Each unit’s productive capacity is 470/470 megawatts.
Related News
Samra Zulfiqar
Samra Zulfiqar is a Real Estate Analyst at Zameen Media (Pvt) Ltd. You can also find and follow her on Google+.