Lahore: The Ravi Urban Development Authority (RUDA) has revealed significant advancements made at Chahar Bagh as construction efforts continue, according to their official Facebook handle on August 23.
Read: River Ravi will rejuvenate in few years: RUDA CEO
As per the details, the latest infrastructure update reflects substantial progress, with earthwork nearly complete at 99%, drainage fully completed, and sewerage works at 98%. The boundary wall is 92% complete, and overhead water tanks have reached 82% completion.
Sub-base and base course works stand at 69%, while water supply installation is at 64%. Overall, the project has achieved 70.6% completion. Stay connected with Zameen News for further updates.