Lahore: The inauguration of the under-construction Chaubucha Phatak Underpass is expected to take place on November 9, according to a news source.
In order to ensure the project’s timely completion, the Lahore Development Authority (LDA) has set October 20 as the deadline for the completion of the mega structure of Chaubucha Phatak Underpass. The carpeting work on the underpass will also begin by this date.
At the moment, finishing work is being carried out on the walls of this underpass, while the roads connecting to it have already been opened to traffic. In addition to that, piling work for the project and the construction of U-turns for the underpass have also been completed. Twenty-one planters will be fitted for the beautification of Chaubucha Phatak Underpass.