Sialkot: According to a news report, Chinese engineers have completed the newly established 8 MW Head Marala Power Project near Sialkot. Mansha Ullah Butt told media on 4th March 2018 that the provincial government has spent USD 35.38 million on this project. The overall project has been supervised by Asian Development Bank (ADB).
The contribution of this energy project is going to add 8 MW to the National Grid. This project was launched in 2014 to be completed by December 2017, but because of delays, is now expected to be inaugurated by the end of March 2018.