Islamabad: The Capital Development Authority has given the construction firm developing Sohan Interchange September 30 as the deadline, according to a news report. Reportedly, the design alteration of Khanna Interchange is the reason why Sohan Interchange has faced delays. So far, only 10% work has been done on the project.
Sohan Interchange will have a total of 32 grids, out of which 14 have been completed. At the moment earthwork for the project has started and the foundation of the overhead bridge is also being laid. With the completion of Khanna Interchange and Sohan Interchange, the road connecting Zero Point to Koral Chowk will become signal free. In the next phase, the road connecting Koral Chowk with GT Road will be widened – an avenue that faces serious traffic problems at the moment.