Peshawar: Project Manager for the Bus Rapid Transit (BRT) project Khalid Mukhtiar, has said that BRT would be completed in time, according to a news report. He explained that out of 1,140 pillars, the construction of 960 pillars is already complete, and that more engineers have been hired to speed up the work further.
He further said that the road leading to Bacha Khan International Airport, as well as Khyber Road have been included in the project. Work on the BRT from Chamkani to Firdous is 90% complete and on Khyber Bazaar to the Amn Chowk section, it is 50% complete.