Stamped contract

I signed a labor contract agreement on stamp paper with my contractor. The contract includes grey structure (including plaster, tiles & marble). Material procurement is my responsibility. So far, we have completed both lenters. All dues to the contractor are clear which means I have paid him for all the work he has done so far. Is there any way for me to exit the contract because I’m not satisfied with the quality of work. In the contract, it is clearly stated that the construction will be done exactly as per drawings. Especially every single beam & column must be placed precisely exactly as per drawings. However, one of the columns is 3 inches out of the wall. I raised this issue with the contractor but he has become very stubborn (badmash) and is giving me a hard time while refusing to accept his mistake. I do not have the patience to deal with him anymore and simply want to get rid of him. I no longer want to continue working with him for the remaining two stages i.e. plaster, tiles & marble . Please let me know if there is a way for me to terminate / exit the contract. Please advise.

This is a big dilemma in Pakistan and quite common. It looks like you did not include a termination clause in the agreement. You can try to settle the matter by asking someone responsible in the area or involve a lawyer.

does this mean i cannot terminate the contract? what could happen if i terminate the contract?