What is the grey structure cost of covered area? I am building 35x64 plot in Islamabad and the cost of grey-structure by constructor is PKR 1350/sqft.
The following is included:
Covered area, PKR 1350/sqft
1- Total area of one house is 1775.00 sft (approx).
2- Excavation in foundation up to 4'.00" as per soil test report.
PCC 1:4:8 in foundation.
3- RCC,columns & raft footings will be completed as per structure drawing.
4- Measurement will be taken from edge to edge of slab.
5- Under ground tank will be completed.
6- Thickness of roof slab will be as per structural engineer drawing.
7- RCC Concrete of roof slab and columns will be as per consultant requirements.
8- Brick work 9" & 4-1/2" thick will be done up to 11.00 feet roof level.
9- Cement plaster will be done with C.M. 1:3 for roof & 1:4 for walls.
10- Floor will be rough finish with 4" PCC 1:4:8 & 2" PCC thick on top.
Electric conduct in roof & walls with under boxes will be provided.
11- Hot & cold water supply will be of PPRC pipes & sewerage will be of pvc pipe 4" & 6" dia12- Sui gas fitting will be of g.I pipe IIL as per requirement.
Outer area working
13- Boundary wall will be completed @ 200/ sft with plaster.
14- RCC parapet wall 3" thick will be completed @ 150 / sft with plaster.
15- Simple flooring in outer area will be 4" PCC 1:4:8 & PCC 1:2:4 2" thick in gully @ 80/sqft.
Note: Water supply & electricity will be provided by client at site free of cost.
I have issue with boundary wall. The constructor said it is 160 ft, and total cost would be 10 (height of wall) x 160 (area) x 200 (per sq ft cost) PKR. My worries are boundary wall should be included in covered area in part of house, where there one is constructing rooms, etc?
In total I have to pay him "27 LAK". Pls let me know, if this cost is justifiable, as i need to start the home asap.
Thank you
Dr sahab,
Are these specifications for top quality construction?
Thanks!
1350 my god. Its way too much.
I would do all of it inside outside covered or not covered in1350. He is charging allot. And why go for an expensive option provide ur own material.its not rocket science and it can save u allot.
@Pk1
I don't know. I am not an experienced person in property and building. I suspect, it shld be average living construction [Single Story]
One of my uncle introduce the constructor with me.
What you think about this cost pls?
@H_T
Does your quote include tiles, doors/windows, and toilet stuff as well?
Thanks
Your cost break down 1000 to 1200 bags cement.5to 6 ton steel. Around 50000 to 60000 bricks. 3 to 5 trucks of sand and gravel each.
Cement is rs.500 each bag
75000 per ton steel.
Bricks@ rs 8 each.
Sand rs 18 persqft 800 feet in one truck.
Gravel rs 30 or 31 per sqft .... Well now u know the math and add an extra rs250 per sqft for the contractor n there is ur total cost of grey structure. Rest is ur choice
MY key to key would be in the range of 1450 to 1650 per sqft with good finishing which will include everything marble woodwork kitchens electricial… Ready to move in but my personal advice is not to give key to key… Here is my email hassan786_99@yahoo.com leave me ur contact details and ill be intouch.
@ Dr...Contractor gave you good price but it can be Rs.1300/sq ft
Dont listen to ppls who make you confuse and you can face more loses if you will do by your own if you dont have any idea/experience.
So better you should must have idea of accurate cost than guessing.
If you will provide your own material you can hardly save Rs.100 to Rs.150 which is contractor share which is justifiable and you will be in peace of mind provided if you take care to check all the material by your own or your consultant.
The above rate should must be inclusive of Safety grills.
We can do it at Rs.1300/sq ft of covered area
Open Area like boundary walls,pcc,overhead tank will be on very reasonable item rates.
Please send me your email addres I will send you detailed list of scope of work in grey Structure works and Finishing works so you can have a bible to follow up your contractor or negotiate.
We are here at your disposal.
Regards
dSA
92-333-4220989
Boundry wall and gate are not included in sq/ft rates they will chare extra.