Dear construction experts and relevant
Aoa
Pls. Advise me on this matter.
I signed a written turn key agreement with a contractor to renovate a 10 marla house as per drawings (drawings given by me includes building, electrical and sewerage drawings. I get separate services of an architect for these drawings).
Before the signing of agreement the contractor visited the site and thoroughly viewed the site and then he gave me final quotation, i got two three more quotation and after comparing the items i selected this contractor.
The contractor violated agreement variously but main violation is time. The agreement to complete was 4 months but after passing 6 months he could not complete the gray structure (its very painful as we shifted to rented house).
2. Other violation is payment plan. He mention in agreement that 10% on different job but he insist to pay more amount for various activities and till yet i had paid 26/27 lacs which is almost 700,000 excess payments (as many activities not yet started/completed).
3. The quility of his work is not as per mentioned standard as he mentioned in his agreement that every activity will be a+ (the best quality available with their firm).
Some other violations which u understand as normal contractor did.
During last 2/3 months i ask him many time (not only personally but also send sms and whattsapp) to speed up my work and complete my work in time but his routine did not changed.
One or two times i want to kick him but my friends (including one witness in agreement) ask me to continue work with him as money will struck so i kept mum to avoid disrupt my work.
Whenever i ask him about delayed work he says that your building was to complex and cost which he gave is too lesser. Although he did not ask to quit the agreement but his delaying tactic suggest me to think otherwise.
Pls. Mention what should do in this situation as i am really disturb in this situation.
Best regards.
Dear Akhtar Sb,
In which city is your project?
If you have written agreement you can do any action if violation did by him..
If you will be scare of taking action you will be looser and further will face loss in delaying and inferior quality.
Take actions if you already faced loss you should not bear more.
This is the difference you ppls pay by getting less price....
Regards
Team dSA
92-333-4220989
Continue this contractor dont kick him because he might have been taken much amount from your account, if you will change your contractor then you have to lost much amount. Because may be other contractor will not consider his work and charge you again. So beer this contractor and take your work from him
regards
Faheam
00923217867889 whats up as well