Aoa, every one i have plan to start construction on my
10.Marla plot in islamabad please i need some information about
Labourer cost without material thanks
Dear Sir,
Masor charges 1000-1200 per day and labourer charges 500-700 per day if hired on daily wages (timings between 8 am to 4 pm in between 12 to 1 pm lunch break and two tea break at 10am and 2 pm for 15 mins)
Another option have contract with some senior mason who will work and will arrange other masons and labour on sq. Feet rate but bind him on legal paper the completion of work on time.
Always keep some retension money from their payments.