guys i am in the process of building a house in karachi, covered area 12000 sq ft.
few questions :
- the contractor says we will need 64 ton of steel with 26.5 ton being used in the basement along with double jaal and retention walls, does that make sense
- cement he says 6300 bags isnt that alot?
- using blocks, how many blocks will be needed any idea
- i am budgeting and i have kept the following for
- tiles (without labour) = 36 lacs
- wood (with labour) = 43 lacs
would this work?