Construction of Villa (10 Marlas = 3,200 covered area) Foundation Completion Target 3 weeks &1 week for Plaster etc Total = 4 weeks [Part-1 of 2]
Description Unit Qty Rate T. Expenses
Labour 3,200 ft x 45= 144,000
Bricks 12 Trollies x 19,000 = 228,000
Cement 150 Bags x 500 =75,000
Crush 800 ft x 38 = 30,400
Bitumen 9 Drum x 1,200 = 10,800
Services 1 Month x 30,000 = 30,000 on Monthly basis
Steel 375 kg x 85 = 31,875
Sand 8 Trollies x 2,200 = 17,600 Standard Tractor trolley
Soil 50 Trollies x 1,200 = 60,000 Standard Tractor trolley
GT =627,675 {196 Rs. Per Sq.ft cost}
FOUNDATION Videos of 10 MARLA House is available at youtube, soon I will upload Ground Floor Videos with actual expenses, Appreciate your suggestions Best wishes,,
https://youtu.be/m1adLivOYiw