Dear friends
Can any brother give me material quantity estimate (how many bricks,how many bags of cement,sarya,sand )for 2900 square ft covered area grey structure.This will help me in tracking the contractor for material requests as i will doing building contractor without material.
My plot is 30*55.Ground floor will have two beds,two baths,one kitchen and one drawing and one tv lounge and first floor will be replica of ground.Second floor will have one room and washroom.
Aamir hassan raja
Aamirrajapk@gmail.Com
Try this calculator and it might give you very rough estimate
Thanks alot
Roots Engineering Services is providing the construction services to our prestigious client for several years . I offer my services to build new house with A+ GRADE Construction as follows
A. GREY STRUCTURE WITH MATERIAL (Rs.1390/sft)
WORK INCLUDED
Super Structure
Surface Rendering
Flooring
Roof Insulation
Electrification
Plumbing Work
B. TURN KEY BASE OR WITH MATERIAL (Rs.2400 to 2650/sft)
WORK INCLUDED
(Include Grey Structure Work & As Mention Below)
- Wood work
Skin panel doors
Solid doors aish wood / kail
Client demands
Aluminum work for All home Windows and Glass (ghani)
Steel staircase.
Face work depending upon your map.
Fancy fire places.
Floor Marble.
Bath Room Tile Flooring.
Fixtures and accessories of baths, kitchen.
False ceiling depending upon…
D. BASEMENT CONSTRUCTION (Rs3500 to 4000 /sft)
(Turn Key Base Or With Material
Grey structure & Finishing work)
NOTE
With awal number bricks and using standard ratio of sand + cement.
Free to ask any question regarding construct new build home
You can construct your own house under your supervision as well if you have any doubt
Regards
Faheam: 03217867889
Construction material quantity estimates for 2900 sq/ft covered area
bricks 75000
cement 280 bag 50 kg per bag
sarya 2500 kg
sand 12 troly
thekeydar sohail 03224745744
Sohail sb according to my calculation 1 kanal house is constructed approx in 1 lac bricks.How 7 marla will consume 75000 bricks…Can u plz explain…May be my calculation is wrong.Plz elaborate how you calculated it.
Bhai wo 1 knal ka nahi 2900 sq ft ka poch rahy hain or wo b coverd area boundry wall nahi shamil or sahi estimate to map daikh kar hi andaza ho ga
Sir 75000:100000 for 7marla:1kanal ki ratio koi fit nahi beth rahi…That is why i asked this.
Agar 7 marla main 75000 lagain to 20 marla yani 1 knal main to pher is hisab say 220000 bricks lagni chahiya mgar ya calculation sahi nahi
Bhai ap ka or mara taqreban aik hi hisab hai 2900 sq ft taqreban 13 marl jga banti hai os hisab say main nay apna andaza lgaya tha
Construction cost depends upon quality of material and design that you select for your dream home. We have a wide range in it and would like to work for you. If you are interested then kindly send us your contact details at hamza.asif@ameradnan.com or call on 042-36655262 for more information. We are working in interior designing and construction field for several years and you can see our work by visiting https://www.facebook.com/AmerAdnanAssociates.
Sohail sb ,
mazrat k sath
230 bags of cement only ?
and 2.5 ton rebars ?
12 trolly sand ? that makes almost 1.5 dumper of sand
this is super sir .
TUSI MAHAN HO SIR
i think management should look into such advices . Spoils THE IMAGE of A website
Sir you would need follows,
7-8 ton rebars (considering footing in base, door beams, plinth ) footed walls with double net on first floor)
50 bags per floor for collums and beams and brick work
almost 100 bags for single roof /lenter (roof each ) based on calculation
30*45 (covered area) /7 (1:2:4 ratio for cement )=192 / 2 (considering roof to be 6 inches thick )
3 dumper of sand and 6 dumper of crush (could be quoting a little bit higher )
at most 40k bricks
regards
Atif Pasha