Plot 1 kanal
Ground floor : 3000 sq.Ft
First floor : 2800
Can anyone give an approximate estimate of steel,cement,gravel and sand in particular and whole grey structure in general.Also,how much time it's gonna take with a normal pace of work to complete grey structure.
Another question i was curious abt is tht which period of year in pakistan should be avoided for construction with respect to too cold,hot or rainy weather when progress of work cannot be maximized.
@curious for all these question you have to contact waseem builder’s. He will guide you in a good way according to your question I also help out him in some question so I will going to post his number thanks waseem builders 03004582022 whats up number 03434477099
@Curious
Rs.1300/sq ft cost you should have in mind for grey structure....
You can start in any season but in working hours utility summer from March onward
the best timings.
Regards
dSA
92-333-4220989
There is a wide range of material and designs that we can show you. You may see our work by visiting Redirecting.... Send us your contact details at hamza.asif@ameradnan.com or call on 042-36655262 to discus in details that is more suitable.
We can provide you detail BOQ. Please send us your architectural and structural drawings. Our BOQ will be precise and save your good amount of money.
Approximately rates grey structure
Ground Floor Rs. 1050/sft
First Floor Rs. 999/sft
Kind Regards,
Ar. Wahab
Arch Five Architects
0321-5674022
Thanks DSA for ur reply.
Cud u plz,give me the rough estimate of sand,gravel,steel and bricks also.
Dear Curious ,
if you have you drawings already sorted please share with us to get you a total estimate for the material required
email: a.muhammad@calrebuilders.com
Roots Engineering Services is providing the construction services to our prestigious client for several years . I offer my services to build new house with A+ GRADE Construction as follows
GREY STRUCTURE WITH MATERIAL
WORK INCLUDED
(Rs.1050/sft)
Super Structure
• Thick masonry up to ceiling level.
• RCC/RBC slabs, Lintels Beams
Surface Rendering
• Application of cement plaster to all the ceilings, internal and external wall surfaces
Flooring
• Compaction of Backfill material, dressing , leveling.
• Laying of Brick Ballast.
• Laying of 2” PCC under flooring
Roof Insulation
• Includes cleaning, coats of hot bitumen, one layer of polythene sheet,
• and 3” to 4” thick mud laid in slope, laying and grouting of 1- 1/2” thick brick tiles.
Electrification
• Conducting, wirings, DB’s fixing only
Plumbing Work
• Sewer Line, Man Holes, Baths hot and cold water pipe lines, overhead pipe line , rain water.
• pipe only( PPR and UPVC Fittings)
NOTE
Executing the job with first class bricks
Standard ratio of sand and cement
Keep maintain quality and standard of work
You can supervise your own work regarding ratio of material and items which I described above
if you have any doubt.
Free to ask any query regarding rate and jobs description.
Regards
Faheam Akhtar
0923217867889
Thank u all for a reply but i wasnt looking to hire any contractor.
My query was simply to get an APPROXIMATE idea of the building material required based on the information given in my post.Im aware of the construction rates but it was quantity tht I wanted figure out.
Any experienced contractor or a civil engineer cud have given tht information but im a bit disappointed tht nobody bothered trying.